Is the contractor entitled to delay penalties if the delay in performing the work results from the other party failing to enable them to commence or from requests for fundamental modifications?
The contractor is not entitled to delay penalties if the delay in performing the work results from the other party failing to enable them to commence at the specified time, or from requests for fundamental modifications that necessitate recalculating the performance period in accordance with the contract terms.
Legal References & Citations
البند الثالث من العقد المبرم بين الطرفين برقم ٠٥١٤ وتاريخ ٤/٥/٢٠٢١م
Share this answer:
About Radiif
Radiif is an AI legal platform specialized in Saudi Arabian law, providing answers verified by legal references and articles.
This answer is for general legal education and is not legal advice. Please consult a licensed attorney for your specific case.
Page Stats
Have additional details about your case? Ask Radiif AI Legal Assistant now...
Enter your case facts or query to get an instant AI analysis verified with Saudi law articles.
Do you want to consult a certified lawyer for this case?
We can suggest a list of certified lawyers with extensive expertise specifically in this domain.