Are the main contractor's pleas concerning defects in the subcontractor's works admissible if final payment certificates were issued after the main contractor became aware of such defects?
Legal Answer
Radiif AI Legal Assistant
⚡ Quick Answer:
The main contractor's pleas concerning defects in the subcontractor's works are not admissible if final payment certificates were issued after the main contractor became aware of such defects (as notified by the project owner), as this constitutes an acknowledgment from him of acceptance of the works.
Legal References & Citations
عدم قبول دفع المدعى عليها بوجود أخطاء في التنفيذ حيث إن المستخلص الأخير جاء عقب خطاب مالك المشروع بوجود الأخطاء فدل إقرار المدعى عليها بالمبلغ محل المطالبة مع علمها بوجود الأخطاء (من أسباب الحكم الابت...
Share this answer:
About Radiif
Radiif is an AI legal platform specialized in Saudi Arabian law, providing answers verified by legal references and articles.
This answer is for general legal education and is not legal advice. Please consult a licensed attorney for your specific case.
Page Stats
Do you have specific details about your case?
Ask Radiif AI Legal Assistant now and get verified answers with exact citations from Saudi law.
Do you want to consult a certified lawyer for this case?
We can suggest a list of certified lawyers with extensive expertise specifically in this domain.